Energy Project Economics: Terms and Definitions

This section covers the financial and economic terms used to evaluate and implement cogeneration and energy projects. Compiled by the engineers and analysts of KTS Engineering.

Project Evaluation Metrics

ROI (Return on Investment)

ROI (Return on Investment) - the ratio of a project's net profit to the invested CAPEX, expressed as a percentage. For cogeneration projects, ROI is calculated as annual energy cost savings divided by the capital investment. With an ROI of 30%, the investment pays back in roughly 3-3.5 years. ROI is easy to calculate but ignores the time value of money - unlike IRR and NPV.

Related terms: payback period · IRR

IRR (Internal Rate of Return)

IRR (Internal Rate of Return) - the discount rate at which a project's NPV equals zero. It can be read as the maximum acceptable cost of capital for the project: if the bank's lending rate is below the IRR, the project can service the loan. For KTS Engineering cogeneration projects, IRR ranges from 20-45% depending on capacity, gas type and electricity tariffs. A high IRR makes cogeneration attractive for bank financing.

Related terms: NPV · ROI

NPV (Net Present Value)

NPV (Net Present Value) - the sum of all future cash flows of a project discounted to the present. A positive NPV means the project creates value over and above the cost of capital. NPV > 0 at the chosen discount rate is the main criterion for the investment decision to build a cogeneration facility. For KTS Engineering projects of 1+ MW, the 15-year NPV ranges from several million to tens of millions of euros.

Payback Period (Simple and Discounted)

Simple payback period (PP) - the time it takes for cumulative energy cost savings to equal the capital investment, without considering the time value of money. For KTS Engineering cogeneration projects based on Jenbacher units, it is 2-4 years with 5,000-8,000 operating hours per year. Discounted payback period (DPP) - the time it takes for the project's NPV to turn positive. At a discount rate of 10-15%, the DPP is 0.5-1.5 years longer than the simple payback period, i.e. 3-6 years. This more conservative estimate is the one banks use when financing projects.

Project Sensitivity Analysis

Sensitivity analysis - an assessment of how changes in key project parameters (electricity tariff, gas price, plant load, CAPEX) affect performance indicators (NPV, IRR, payback period). It shows how far the electricity tariff can fall or the gas price can rise before the project stops being profitable. KTS Engineering performs sensitivity analysis as part of the feasibility study to assess project risks.

Annual Economic Benefit of Cogeneration

Annual economic benefit of cogeneration - the total annual savings a company gains from operating a cogeneration plant. It includes:

  • savings on grid electricity purchases: the difference between the tariff and the cost of on-site generation;
  • savings on heat supply: replacing purchased heat or gas burned in boilers;
  • revenue from selling surplus electricity to the grid (where permitted).

Documented KTS Engineering results: energy costs cut by 51% at a soft drinks plant and by 40%+ at industrial facilities.

Financing Models

Energy Equipment Loan (OTP Bank)

Energy equipment loan - a bank loan to finance the CAPEX of a cogeneration project. KTS Engineering works with OTP Bank to provide loans for customers purchasing Jenbacher units. Loan repayments are covered by the energy cost savings delivered by the cogeneration plant - in effect, the plant pays for itself. The customer becomes the full owner of the equipment from day one.

Energy Equipment Leasing (TEKOM LEASING)

Energy equipment leasing - a finance lease of a cogeneration plant with a purchase option at the end of the contract. KTS Engineering works with TEKOM LEASING. Benefits of leasing:

  • minimal or zero down payment;
  • monthly payments from operating cash flow (out of energy cost savings);
  • lease payments are treated as expenses, reducing corporate income tax;
  • ownership of the equipment transfers at the end of the contract.
ESCO (Energy Service Contract)

ESCO (Energy Service Company; energy service contract) - a financing model in which KTS Engineering invests its own funds in building a cogeneration plant at the customer's site. The customer invests nothing: it pays KTS Engineering out of the energy cost savings the plant delivers. When the contract term (5-15 years) ends, ownership of the plant transfers to the customer. ESCO is ideal for companies without spare investment capital.

Synonyms: energy service contract · energy performance contracting (EPC)

PPA (Power Purchase Agreement)

PPA (Power Purchase Agreement) - a long-term contract for the purchase of electricity at a fixed price between a generator (the owner of a cogeneration facility) and a consumer. For cogeneration facilities, a PPA makes it possible to structure electricity sales to an anchor consumer (a company on the same site or sharing infrastructure) for 5-20 years at a price below the grid tariff. A PPA is the financial basis for raising project finance.

Feed-in Tariff

Feed-in tariff ("green tariff") - a special purchase price for electricity from renewable sources (biogas, landfill gas, solar, wind) at which the state guarantees to buy all the electricity generated. In Ukraine, the feed-in tariff for biogas was set in euro cents per kWh and was the key driver of biogas project economics in 2012-2020. After the electricity market reform (2020), the renewable support model changed. Please check the current terms with KTS Engineering.

Related terms: feed-in tariff for biogas

Day-Ahead Market (DAM)

Day-ahead market (DAM) - a wholesale electricity market where generators and buyers trade electricity for delivery the next day at the market price. Cogeneration facilities of 1 MW and above can sell surplus electricity on the DAM as generators, earning additional revenue. Entering the DAM requires market participant status and compliance with the technical requirements of the regulator, NEURC (National Energy and Utilities Regulatory Commission of Ukraine).