Cogeneration Plant Construction and Installation: Terms and Definitions

This section contains terms related to the design, construction, installation and gas supply systems of cogeneration facilities. KTS Engineering delivers the full EPC cycle, from feasibility study to commissioning.

EPC Engineering

EPC (Engineering, Procurement, Construction)

EPC (Engineering, Procurement, Construction) - a turnkey contract under which the contractor (KTS Engineering) takes full responsibility for the design, equipment procurement and construction and installation works of a cogeneration facility. The customer receives a finished, operational facility without having to manage multiple subcontractors. KTS Engineering delivers EPC projects from feasibility study to commissioning, followed by long-term service.

Synonyms: EPC contract · general contracting · turnkey construction

EPCM Contract

EPCM (Engineering, Procurement, Construction Management) - a contract under which the contractor (KTS Engineering) handles design, equipment procurement and construction management, while the construction and installation works are carried out by specialist contractors. Unlike EPC, the customer retains more control over the construction process but takes on part of the risk. EPCM is used for large facilities where the customer has its own construction department.

Feasibility Study

Feasibility study - a document confirming the technical viability and economic soundness of building a cogeneration facility. It includes an analysis of the company's electricity and heat consumption, selection of the gas engine genset type and capacity, CAPEX and OPEX estimates, and calculation of the payback period, IRR and NPV. KTS Engineering prepares the feasibility study free of charge at the pre-design stage, so the project economics can be assessed before the investment decision is made.

Energy Audit

Energy audit - a comprehensive survey of a company's energy infrastructure to identify opportunities for reducing energy costs. For cogeneration projects, the energy audit establishes the actual electricity and heat consumption profile by hour of day and season of the year - the input data for choosing the optimal cogeneration plant configuration. KTS Engineering performs the energy audit at the first stage of design.

Detailed Design

Detailed design - development of the complete set of design and cost estimate documentation required to build a cogeneration facility: site plan, civil and structural section (engine room, foundations), thermal flow diagram, power supply diagram, gas supply diagram, process control system and environmental protection section. The detailed design undergoes expert review and is the basis for obtaining construction permits and the gas grid connection.

Power Plant Configuration and Capacity Sizing

Power plant configuration - determining the number, capacity and type of units in a cogeneration plant based on the electricity and heat consumption profile, the site's technical constraints and the redundancy requirements. Typical configurations:

  • a single Jenbacher unit - for a stable load with 100% grid backup;
  • two units in an n+1 arrangement - for higher reliability requirements;
  • several units in a modular power plant - for loads of 5 MW and above.

KTS Engineering calculates the optimal configuration free of charge.

Energy and Thermal Modeling

Energy and thermal modeling - an hour-by-hour calculation of the balance between electricity and heat production and consumption at a cogeneration facility over a year. It determines annual electricity and heat output, the number of hours in grid-parallel and island operation, and the amount of heat that must be dumped through the emergency air cooler. The modeling results are the input data for calculating the project economics.

Installation and Commissioning

Construction and Installation Works

Construction and installation works - the complete scope of on-site work from site preparation to equipment installation: earthworks, unit foundations, construction or renovation of the engine room, cable routing, installation of gas and heating pipework, and equipment installation. KTS Engineering carries out construction and installation works with its own crews or with certified subcontractors.

Installation Supervision

Installation supervision - technical supervision by the equipment manufacturer's specialist (KTS Engineering as INNIO's authorized representative) of a gas engine genset installation carried out by the customer's construction contractor. The supervising engineer checks that the unit is correctly placed on its foundation, that the gas, electrical and heating connections are correct, and that the installation complies with the manufacturer's requirements. Without installation supervision, the INNIO factory warranty does not cover the facility.

Unit Alignment

Unit alignment - precise alignment of the engine and generator shafts (or engine and compressor shafts) relative to each other before the connecting coupling is installed. Incorrect alignment causes increased vibration and accelerated wear of the bearings and coupling, and severe misalignment can destroy the coupling in operation. Alignment is performed with a laser alignment tool to an accuracy of 0.01 mm. KTS Engineering performs alignment at every installation and after a major overhaul.

Vibration Isolation

Vibration isolation - a system of resilient elements (vibration isolators, anti-vibration mats, spring mounts) between the unit's base frame and the building structure to reduce the transmission of vibration from the running engine to the building. Proper vibration isolation is a mandatory requirement for cogeneration plants in residential or office buildings. KTS Engineering designs and installs vibration isolation systems for all types of gas engine gensets.

Gas Train

Gas train - the system of piping and valves connecting the company's gas pipeline to the gas path of the genset engine. It includes the gas supply line, a gas pressure regulating station with a pressure regulator, shut-off valves, a gas meter and an emergency shut-off solenoid valve. The gas train is designed and installed in accordance with Ukrainian gas supply standards (DSTU) and building codes (DBN).

Electrical Connections

Electrical connections - the set of electrical links between the cogeneration plant and the company's network: the cable line from the generator to the main distribution board (MDB), a power transformer, switchgear, relay protection devices and an ATS. The electrical connections are installed in accordance with the Electrical Installation Code (PUE) and the requirements of the grid company.

Commissioning

Commissioning - the final stage of cogeneration plant installation before it is put into operation:

  • programming and configuring the DIA.NE controller;
  • setting up the gas path (pressure, flow);
  • first start-up and combustion tuning;
  • setting up protections and interlocks;
  • grid synchronization and load ramp-up;
  • a test run at 100% load for several hours with measurement of all parameters.

Commissioning is performed exclusively by authorized KTS Engineering engineers. The INNIO factory warranty takes effect once commissioning has been successfully completed.

Putting into Operation

Putting into operation - the formal confirmation that a cogeneration facility is ready for commercial operation: signing the acceptance certificates for the construction and installation works, the commissioning and test reports, and the technical documentation. Facilities connected to the power grid also require the grid company's permission for parallel operation. KTS Engineering prepares the complete as-built documentation package and assists in obtaining all permits.

Gas Supply Systems

Gas Pressure Regulating Station

Gas pressure regulating station - the gas supply unit that reduces the pressure of natural gas from pipeline pressure (0.3-12 bar) to the working pressure of the gas engine (50-500 mbar). It includes a slam-shut valve (SSV), a pressure regulator, a relief valve, a gas filter, a gas odorizer (if required) and pressure monitoring instruments. KTS Engineering designs and installs regulating stations for cogeneration plants in line with INNIO's requirements for the gas pressure at the engine inlet.

Synonyms: gas regulating unit · pressure reducing station · cabinet-type regulator station

Gas Pressure Regulator

Gas pressure regulator - the main component of a pressure regulating station: a mechanical device that automatically maintains the outlet gas pressure at a set level regardless of changes in inlet pressure and flow. It works by means of a diaphragm or spring-loaded valve controlled by the outlet pressure. Jenbacher gensets use regulators with an outlet pressure of 100-500 mbar and a capacity matching the engine's gas consumption (100-3,000 m³/h).

Gas Pipeline Shut-off Valves

Gas pipeline shut-off valves - valves, cocks and gate valves that shut off the gas flow in various operating and emergency modes. Cogeneration facilities use:

  • Ball valves - manual shut-off for maintenance;
  • Solenoid valves - automatic emergency gas shut-off on a signal from the gas detector or ESD;
  • Slam-shut valves (SSV) - trip when the gas pressure is exceeded.
Gas Meter (Flow Meter)

Gas meter (flow meter) - an instrument for measuring the volume or flow of natural gas consumed by a cogeneration plant. Types in use: rotary meters, turbine meters, ultrasonic meters and diaphragm meters. The commercial gas metering station undergoes metrological verification and is sealed. Meter data are used for billing with the gas supplier and for monitoring the engine's specific gas consumption.

Synonyms: gas flow meter · gas metering station · fiscal gas meter

Engine Room Fire and Explosion Protection

Engine room fire and explosion protection - a set of technical measures to prevent and contain fire and explosion hazards in a cogeneration plant room. It includes:

  • Gas detectors (methane sensors) with alarms and automatic gas shut-off;
  • A fire alarm system with smoke and heat detectors;
  • An automatic gaseous fire suppression system (Novec, CO2, halocarbon) or a sprinkler system;
  • Forced ventilation of the engine room (at least 10 air changes per hour);
  • Explosion-proof electrical equipment in Zone 2 areas according to IEC 60079.